2006
Back-log
| • SOLARGENIX,
Nevada Solar One |
| • NATCO |
| • TXU,
Sandow Projects |
| • NFS, Plant Modifications |
| • BRAZOS ELECTRIC COOPERATIVE |
| • ETHYL CHEM, LTD |
| • SIEMENS, Mustang Station
Unit 5 |
| • FIELD SERVICES |
Current
Projects (EPC)
| Solargenix
Nevada Solar One: Boulder City, NV |
| 
Upcoming Milestones:
• Solar Field equipment erection
50% complete by September 15th
• Solar field foundations Installation
100% complete by October 15th
• Turbine generator Foundation
100% complete by October 15th.
|
Lauren
Engineers & Constructors is responsible for the engineering,
procurement, fabrication and construction of a 64-megawatt
solar thermal electric generating facility south of Las
Vegas, Nevada. Through August 27th, 420,191 man-hours have
been expended by direct hire and subcontract personnel on
the project. Approximately 25,000 engineering hours have
been expended of the 42,000 budgeted hours (58%). Major
mechanical equipment procurement is 51% complete by the
number of pieces of equipment. 15 of an estimated 25 subcontractors
have been issued for the project. Solar Field fabricated
piping is underway—the shop has fabricated and delivered
104 spools to the site. Lauren is currently working with
suppliers to increase production and improve the delivery
schedule of the solar field metals to support construction
efforts and meet the 50% complete milestone by September
15th. The workforce is up to 674 personnel, and 384,000
work-hours have been expended by direct-hire Lauren employees
out of 1,100,000 work-hours projected for the project. Project
Milestone achieve on July 15th was solar field foundations
installation was 50 % complete. |
Current
Projects– Industrial Services |
| TXU - Rockdale, TX |
 |
Sandow Power Plant
Scrubber Modification Existing Plant Switchgear Existing Plant
Exciter
|
| EBAA Iron, Inc. Eastland,
TX |
 |
T & M Maintenance Contract
|
| Nuclear Fuels Services - Erwin,
TN |
 |
Plant Modifications Contract
|
| Converteam Wingate, TX |
 |
Horse Hollow Wind Farm
Replace Existing Internals of DC/AC Converter |
Current Projects
- Fabrication
| Solargenix
|
 |
Solar
Field Metals Fabrication, Sleeper Rack & Pipe
Shoes, Miscellaneous Steel |
|
| NATCO
|
 |
ASME
Code Vessels/Amine Plants
|
|
| GE/Ionics—RCC
Japan |
 |
Process
Equipment Skids
|
|
| NATCO
|
 |
Amine
Skid
|
|
Current
Projects - Engineering • Texas
Utilities - Various TX Power Stations
Miscellaneous TXU Projects
• Horsehead
Corp.—Rockwood, TN
New Kiln for Zinc Reclamation
• Golden
Spread Cooperative—Denver City, TX
Mustang
Power Station, Unit 5
• Brazos
Electric Coop. – Waco, TX
Mobile
Kimball Rd. Substations Design
• St.
Gobain—Bryan, TX
Pendulum Kiln & Line 4 Relocation
• Nuclear
Fuels Services - Erwin, TN
Continuing Engineering Services
• Siemens
- Salt Lake City, UT
Lakeside Power Project
• Lone Star Ethanol Plant– TX
Preliminary Plant Design
• Ethylchem Ethanol Dehydration Facility –
Trinidad
Engineering Design
• Omya Alabama, Inc. - Sylacauga, AL
Detailed Engineering for New Facility
• Ethyl Chem, LTD - Trinidad
Conceptual Design of an Ethanol Dehydration
Unit. Lauren is slated to begin construction
management services in early '06.
• Murphy Oil—Superior, WI
No. 2 Cooling Tower Study
• Johnson—Matthey, Sevierville, TN
JMI Project from Plant #1 to Plant #2
Project
Updates
SUCCESSFUL COMPLETION OF NAVAJO JP8 PROJECT FOR LEC
|

Project Turnover of JP8
Unit Terry Pittman, Site Manager to Robert
Torres, Navajo Refining Operations Supervisor
|
Lauren
Engineers & Constructors completed the JP8 revamp
project for Navajo Refining in Artesia, New Mexico in
June. Numerous projects in the refinery were coming
to completion at approximately the same time frame and
Lauren completed the JP8 unit ahead of the Navajo Startup
schedule. The project achieved a perfect safety record
with no recordable or lost time injuries, no plant incidents
and no accidents. The project peaked at 64 on-site personnel.
A big thanks goes out to the project team on-site and
in Abilene for the “above and beyond” efforts
to bring this project in safely and on schedule. Terry
Pittman-Site Manager, Phil Gillam-Site Superintendent,
Wayne (Buckwheat) Fields-Pipe Supervisor, Johnny Miles-Mechanical
Supervisor, Monty Hambrick-Safety Supervisor, and all
the project team performed in an outstanding manner.
The fabrication shop, including Richard Bruton, Curtis
McAllister and Carl Croft, did a great job in keeping
the pipe spools on schedule with practically no errors.
Kirk Boswell, Alan Hewitt and David Joiner were also
instrumental in quickly working through potential delays
and in performing final checkout and turn-over activities.
Everyone who had a part on the project team did a great
job of working together and staying focused on client
satisfaction. |
LAUREN E&C, ULC - ALBERTA,
CANADA |

Cogeneration Team members
Brenda Murphy, Human Resources & Luc DeGrace,
Site Services Coordinator.
|
Lauren’s
E&C, ULC’s Alberta based Construction Management
Team is now onsite in the oil sands of Northern Alberta
and has successfully kick-started their effort on the
Cogeneration Project.
Currently the team has over 20 Lauren employees onsite.
This team is growing and getting better all the time.
At this rate we fully anticipate being staffed-up by
the end of September to our full requirements. Since
its inception, the role of the Project Team has been
to strategically coordinate efforts to manage the construction
of the Cogeneration Plant required for a bitumen processing
plant located in the oil sands north of Fort McMurray,
Alberta. The contractors
we are working with are making a significant effort
to bring us inline to where we need to be to meet contract
dates. The site team intends to have 80% of the concrete
in place by the end of October 2006. This will allow
for the construction of required buildings to occur
and for the instillation of available equipment. Much
of this work will be done in cold weather conditions
that are characteristic of this northern region during
the winter months.
|
|
Through
Week Ending September 22, 2006
Total Manhours = 1,075,836
Lost Time Incident Rate = 0.19
Total Incident Rate = 1.86
Community
 |

Join the Lauren Team! On
October 6th & 7th
Lauren/Habitat Partner Project
Lauren Team. We have another great
opportunity to serve our community by partnering with
Habitat for Humanity in Abilene. For those of you who
participated in the initial Lauren/Habitat partner project,
you know that this is a great time to get to know your
coworkers better and to help a family in need. This
project presents a unique opportunity because we will
be continuing the work from our first project at 1126
Burger St. This time, though, we will be doing mainly
interior work (painting, installing cabinets, doors,
baseboards, etc.) to get the house ready for the future
owners to move in. As with the last project, we are
going to have three work shifts – Friday, October
6, 12:30-4:30; Saturday, October 7, 8:30 – 12:30;
and Saturday, 12:30-4:30. You are invited to sign up
for any or all of the shifts. Meals and refreshments
will be provided and you get a cool t-shirt, too. What
more could you ask for? Free food and drinks, a free
t-shirt, and, most importantly, knowing that you are
helping someone who truly needs it. So, come be a part
of the Lauren Team as we continue to strive to make
a difference in our community by “serving to build
a better tomorrow, today!”
To sign up, email jody.lee@laurenec.com
|
|
| The Lauren Store |
|
 |
The Lauren Store
is a service provided to Lauren employees which allows
you to purchase quality, branded products at affordable
prices. There are a wide variety of products to choose
from, such as apparel items, sports and leisure items,
and desk accessories. We have worked hard to bring you
great products at a great price, which was made possible
through Lauren's generous agreement to assume all shipping,
tax and branding fees associated with these items. Purchasing
items is a great way to show your Lauren pride. So come
browse the Lauren Store and see what is offered at http://www.laurenec.com/lauren_store.php
|
|
| Softball |
|
| |
Lauren began an annual
slow-pitch softball tradition last year and has carried
it on this year, assembling both men’s and co-ed
softball teams. The men’s team (Lauren 1) consists
of 12 Lauren Employees from the general office, Cypress
office and the Fabrication shop. The Co-ed team (Lauren
2) has 11 players and consists of men and women from all
of the Abilene offices, as well as a few family members.
The softball season lasts 10 weeks, with the men’s
team playing on Tuesday nights and the co-ed team playing
on Wednesday nights. Game times are at 7:30, 8:30, or
9:30. The games are played at Nelson Park (next to the
Zoo). Kevin Porter may be contacted regarding game times.
Come support your Lauren team as they “steal”
the show. |
|
|
| Lauren
Spotlight |
 |
The
Lauren Lantern is published for our valuable employees like:
Jan & Stan Adams
Nevada Solar One Project
Boulder City, Nevada
|
| |
|
| Last month
Lauren Engineers & Constructors, Inc. management team
met in Thurber Texas. This was a productive meeting and
we came away committed to a thematic goal of “Developing
and Implementing Structure and Processes to prepare for
future growth”. This is to be the overriding goal
for Lauren over the next six to twelve months. We broke
this goal down further into five initiatives and listed
actions and metrics for these initiatives. The five initiatives
are (1) Finish implementing Dynamics (2) Define and develop
high performance teams (3) Identify markets and strengthen
Lauren within them (4) Define and develop processes and
(5) Develop and integrate current and new personnel. We
have already made excellent progress on the Dynamics Initiative.
Jeff Hocke was appointed the Dynamics team leader and
has proven himself to be a great leader. He has the Dynamics
implementation process well organized and is effectively
driving the overall Dynamics implementation. Functional
Area Sub Teams (FAST) have been identified and are being
led by the department managers most closely connected
to each particular process and staffed with cross-functional
team members from other departments. These FAST teams
are finalizing process flows, identifying issues, developing
training plans, etc. We appear to be well on our way to
successfully completing the Dynamics implementation effort.
My thanks to all for your hard work and patience throughout
a very difficult and sometimes painful process.
Development of high performance teams must begin at the
top. The Lauren Engineers & Constructors, Inc. executive
management team has begun an intensive team building process.
It became immediately evident that there is yet a higher
team to be formed that includes Lauren Engineers &
Constructors, Inc.’s sister companies to the North,
Kamtech Services, Inc., and Lauren E&C, Inc. We will
begin the process of defining and developing Lauren Holding’s
first team during the month of October at our Fall Manager’s
Retreat. It is my belief that the first two initiatives
are of such urgency and importance that we will be unable
to begin significant actions on the remaining three initiatives
until after the October meeting.
The energy crisis facing the world offers Lauren almost
limitless opportunities to “expand the place of
our tent” (Isaiah 54:2-4). Developing and implementing
structure and processes to prepare us for future growth
must be our number one goal if we are to be prepared to
receive these blessings and excel in the engineering and
construction marketplace. I look forward to participating
with you in growing our business with integrity and skill.
Thank you for all that each of you has already done and
for your continuing commitment to our future.
God Bless,
Cleve Whitener
|
|